Contract Garment Manufacturing: CMT vs Full Package and How to Work With a Factory

How contract garment manufacturing works: CMT versus full package (FOB), the tech pack, factory screening and lead-time checks, default contract rules under Turkish law, and acceptance on delivery.

Zeynep Arslan Contract Manufacturing and Workshop Editor
Published:
Updated:
19 min read
Fact-checked by:
Gizem Polat

Key facts

  • Define scope in writing, prepare the tech pack, collect at least three quotes, sign a written agreement, approve a pre-production sample, monitor production and record acceptance.
  • TDK defines fason üretim as production placed with another firm with the materials supplied by the brand owner, so the first question is always who supplies what.
  • In CMT the factory is paid for the process and the buyer owns the fabric; in full package the factory sources and finances fabric and trims (Gereffi and Frederick, 2010).
  • FOB is in fact an Incoterms delivery term specific to sea and inland waterway transport, but the trade also uses it to mean full-package production.
  • Daily output = direct operators × net working minutes per day × efficiency ÷ SMV; fabric intake, cutting and pressing-packing sit outside this calculation.

The right sequence for working with a contract garment manufacturer is: define the product and the scope in writing, prepare the tech pack, collect at least three quotes for the same scope, put the agreement in writing, approve a pre-production sample, monitor production with in-line checks, and record the acceptance inspection on delivery. The Turkish Language Association dictionary (TDK) defines “fason üretim”, the Turkish term for contract manufacturing, as production placed with another firm with the materials supplied by the brand owner. That is why the first question is always the same: who supplies what?

This guide maps the whole relationship with examples from ready-to-wear: the models, the process steps, the tech pack and capacity check, the default rules of Turkish contract law, and the control points during production. Price calculation, agreement clauses, Turkish VAT withholding and factory selection criteria have their own articles; here we only show where they enter the process. To find and vet Turkish factories in the first place, see clothing manufacturers in Turkey. Legal and tax information is general, is valid as of the date of this article (October 8, 2026) and does not replace advice.

Contract manufacturing models: sewing only, CMT and full package

Contract manufacturing is not one model; what separates the models is who takes on the materials and which production steps. According to a World Bank study (Gereffi and Frederick, 2010), in CMT (cut, make, trim) the manufacturer cuts and sews fabric supplied by the customer to the customer’s specification. It generally takes no part in design, charges for the process rather than the product, and the fabric belongs to the buyer. In full-package production (known in the trade as OEM, FOB or package contractor) the manufacturer sources and finances the fabric and trims and does all of the production, finishing and packing. A manufacturer that also takes on the design is called an ODM in the same study. The study uses “full package” for OEM in one place and for ODM in another. Because terms drift from source to source, read a quotation line by line rather than by its label.

Item CMT (cut, make, trim) Full package (OEM / FOB)
What you pay for The process: cutting, sewing, finishing The unit price of the product
Fabric (main raw material) You supply it; it belongs to you The manufacturer sources and finances it
Trims and accessories Written into the quote: who supplies them, and are they in the price? The manufacturer sources them; scope written into the quote
Tech pack, measurement chart, approved sample You You (the manufacturer, in ODM)
Your main burden Material sourcing, shipping, fabric accounting and quality inspection Specification, sample approval, quality control and the right to approve the manufacturer’s suppliers
VAT treatment in Turkey Treated as contract work (see below) If the workshop supplies the materials, clarify the nature of the work and the invoicing with an accountant

The first four rows follow the definitions of Gereffi and Frederick, the VAT row follows the Turkish VAT General Implementation Communiqué, and the “your main burden” row is Tekstil Rehberi’s assessment. In the end, the agreement decides who holds which item. A note on terminology: FOB (Free On Board) is in fact an international trade delivery term. In Incoterms 2020 it is a rule specific to sea and inland waterway transport, and delivery takes place at the named port of loading. The trade also uses it to describe a contract full-package manufacturer (Gereffi and Frederick, 2010). When you see an “FOB price” on a quotation, ask both who owns the materials and where delivery takes place.

The distinction has a tax side too. Section I/C-2.1.3.2.7.2 of the Turkish VAT General Implementation Communiqué makes it a condition of contract work (“fason imalat”) that the raw materials, above all the main raw material, are supplied by the party who commissions the work. Where a full-package workshop supplies the materials, have an accountant assess the tax nature of the work and the invoicing; if you buy from outside Turkey, ask your supplier in writing how your order will be invoiced.

Which model suits which situation?

  • CMT: suits you if you want to choose and inspect the fabric and trims yourself, work directly with your own fabric supplier, and can finance the materials. The price: fabric arriving on time and complete, wastage, and tracking of leftover fabric are your job.
  • Full package: suits you if you have no team to manage the supply chain or prefer a single counterpart. The price: because material selection and supplier control sit with the manufacturer, part of your control goes with them. Give the fabric and trim specification in writing and write your approval right into the agreement.
  • Sewing only: if you have the cutting done elsewhere or do it yourself, you send the workshop cut parts. The workshop then prices only sewing and finishing.

These are Tekstil Rehberi’s assessments; what decides is the complexity of your product, the size of your order and your team’s capacity to manage supply. Private label is not a production model but a concept describing whose brand the product is sold under: according to PLMA, products that carry the retailer’s name or its own private brands. Such products can also be made by CMT or full package, and the scope question stays the same.

Splitting production into stages

Contract work can cover the whole product or be split into stages: cutting, sewing and printing can be done in separate workshops, and washing and pressing-and-packing can be finished somewhere else again. The Turkish VAT General Implementation Communiqué states that a finished product may be made as contract work as a whole or partly, by production stage. The price of that flexibility is coordination: transport between workshops, wastage at every stage, the limit of each party’s responsibility, and the way a delay at one link passes down the whole chain are all yours to manage.

Turkish contract-manufacturing terms decoded

Quotations, emails and agreements from Turkish workshops use local trade words. This table maps the ones in this guide to the English terms you would use in a tech pack or an agreement.

Turkish term English term What to note
fason (üretim) contract manufacturing, contract work TDK: production placed with another firm, materials supplied by the brand owner
kes-dik-teslim CMT (cut, make, trim) Process fee; fabric belongs to the buyer
tam paket full package Also called OEM or FOB in the trade; check the scope line by line
teknik föy tech pack Drawing, measurements, tolerances, construction details
numune sample Approved sample is the reference for production
termin delivery date, lead time Write the delivery date and the fabric arrival date separately
ütü-paket pressing and packing Last stage before shipping; outside the sewing-line calculation below
alt fason sub-subcontracting The workshop passes your work to another workshop; SOMO’s fact sheet on the practice is titled “Hidden subcontracting”
sevk irsaliyesi dispatch note (delivery note) Record the roll count and the metres or kilograms of fabric

The contract manufacturing process: eight steps from brief to close-out

The table below shows what output should be kept in writing at each step. We give no durations because they change with the product, the workshop and the season.

Step What you do Written output
1. Scope and model CMT or full package? Which stages are contracted out? Who supplies what? Scope note: an item-by-item “who holds it” list
2. Tech pack and brief Define the product, quantity, size breakdown, quality and lead time Tech pack, bill of materials, size-colour-quantity table
3. Quotes and workshop selection Collect at least three quotes for the same scope; assess the workshop against criteria Comparison table
4. Agreement and invoicing method Lead time, quality, wastage, payment, confidentiality; VAT and invoicing Signed agreement, accountant’s view
5. Sample and pre-production approval Approve the sample for measurements, workmanship, trims and labels Approved sample (the reference for production)
6. Material shipment and fabric intake Hand over fabric and trims against a count; check on arrival Dispatch note, intake inspection note
7. Production monitoring In-line checks, output report, lead-time deviation Weekly output report, inspection findings
8. Acceptance and close-out Sampling-based final inspection; acceptance or rejection, payment, review Final inspection report, acceptance or rejection letter

Quotes come side by side at step 3. How a quote’s figure is built, and how to equalise the scope, is covered in the article on contract T-shirt sewing prices. The details of step 4 are in the article on the manufacturing agreement and those of step 5 in the article on the sampling process; both are reachable from the relevant sections below.

Before you hand over the job: the tech pack and brief package

For the workshop to quote correctly, and to avoid a later “we did not know that” dispute, the package must be complete from the start. This is the common practice in the sector; adapt it to your product:

  1. Tech pack: product drawing, measurement chart and tolerances, stitch and operation types, positions of labels and care instructions, packing and folding details.
  2. Bill of materials: fabric (composition, weight, width), trims, thread; and who will supply each.
  3. Size, colour and quantity breakdown: the breakdown affects the workshop’s plan as much as the total quantity does.
  4. Quality expectations: measurement tolerance, AQL level, acceptance and rejection criteria, defect classes.
  5. Lead time: write the delivery date and the date the fabric must reach the workshop separately.
  6. Approval authority: who will approve the sample and any later changes, and through which channel.

For help with the tech pack, patterns or sample preparation, you can turn to firms offering pattern making and sample room services. Changing the style after approval disrupts production. SOMO’s fact sheet on hidden subcontracting (2015) lists changes to design, quantity and schedule made after sample approval, without adjusting price and time, among the buyer-side causes that put pressure on a manufacturer and can trigger subcontracting.

Company directory

Browse companies in the related categories or get quotes from several companies with one form.

Do you manufacture or offer services in this field?

Screening factories and checking capacity

The ten criteria for assessing a workshop are in the article on how to choose a contract workshop. Before you collect quotes, three questions do the first screening:

  • Similar work experience: is there a reference sample, made with a similar product and fabric, that you can see?
  • Capacity fit: do the machine park, the headcount and the other jobs the workshop has taken in the same period fit your order? Turkey’s Ministry of Trade says in its Ready-to-Wear Sector Report 2026 that most businesses in the sector are small and medium-sized. Capacity in workshops of that size may be limited, and according to SOMO, factories often work for many customers at the same time. SOMO also lists a headcount that does not match the production volume, seen when you visit a workshop, as a red flag.
  • Subcontracting policy: does the workshop give part of the work to another workshop? If so, which stage, to whom, and with your permission?

You can find firms that do contract sewing on the CMT sewing workshops page; check these questions for each firm yourself.

Is the lead time realistic? A simple capacity check

To judge whether the lead time in a quote will hold, you can calculate the daily capacity of the sewing line. SMV (standard minute value) is the time needed to sew one product under standard conditions; in the ILO’s work-study reference, standard time is expressed as standard minutes per piece. Efficiency is the standard-minute equivalent of the work produced divided by the total operator minutes spent (number of operators × minutes worked); the ILO gives the same ratio as a performance measure. From these, the following formula for daily capacity is derived (the derivation is Tekstil Rehberi’s own):

Daily output = direct operators on the line × net working minutes per day × efficiency ÷ SMV

The figures below are entirely hypothetical, not market values; replace them with your own inputs.

Input Example value (assumption)
Order 4,500 pieces
Direct operators on the line 15 people
Net working time per day (breaks and set-up deducted) 450 minutes
Efficiency 60%
SMV of the style 9.00 minutes per piece

In the base case, daily output is 15 × 450 × 0.60 ÷ 9.00 = 450 pieces, and the duration is 4,500 ÷ 450 = 10 working days. When the inputs change, the result moves like this:

Scenario Pieces per day Working days needed
Base case 450 10
Efficiency falls to 50% 375 12
Operators fall to 12 360 13 (12.5 rounded up)

This calculation covers the sewing line only. The time for fabric intake and cutting, sample approval, pressing-and-packing and shipping is added separately; your lead time is the sum of them. If you supply the fabric, the lead time depends on the date the fabric reaches the workshop: SOMO lists late arrival of inputs such as fabric among the reasons manufacturers pass work partly or wholly to subcontractors. Ask the workshop for its SMV and efficiency assumptions in writing. How SMV feeds into the price is explained in the article on contract T-shirt sewing prices, linked above.

This section describes the default rules of Turkish contract law for readers whose agreement is with a Turkish workshop. Which law governs your agreement, and whether these rules apply to your case, are matters for the agreement itself and for your lawyer.

A contract in which the contractor undertakes to produce a work and the client to pay a price for it is regulated as a contract for work (“eser sözleşmesi”) in the Turkish Code of Obligations (TBK, Art. 470). A contract-sewing relationship in which you supply the material may fit this definition: the Court of Cassation (Yargıtay) has treated contract-sewing relationships in which the client supplied the fabric as contracts for work (for example 15th Civil Chamber, 2017/2037 E., 2018/3366 K., 24.09.2018; 2018/3517 E., 2019/1255 K., 20.03.2019). Even so, your legal adviser decides which contract type your relationship falls under and which provisions apply. The table summarises what the rules may mean in practice; article texts are based on Law No. 6098 as published on mevzuat.gov.tr on the date of this article (October 8, 2026).

Subject Statutory rule (TBK) In practice
Duty of care (Art. 471/1-2) The contractor performs with loyalty and care, protecting the client’s legitimate interests; the standard is that of a prudent contractor acting in line with professional and technical rules Make the expectation concrete: measurement tolerance, AQL, approved sample. General phrases such as “good workmanship” invite disputes
Having the work done by others (Art. 471/3) The contractor must make the work itself or have it made under its own management; if its personal qualities do not matter, it may also have the work done by someone else The competence of the workshop you chose does not extend to another workshop. Write subcontracting permission and notification into the agreement
Material you supply (Art. 472/2-3) The contractor uses the material with care, accounts for it and returns what is left. It must immediately notify the client that the material is defective, or of any circumstance endangering timely or proper performance, and is liable for the consequences if it does not Hand over fabric against a count, ask for a written account of wastage and leftover fabric, and set the notification channel
Delay and progress (Art. 473) The client may withdraw without waiting for the delivery date if the contractor does not start on time, delays the work in breach of the contract, or it becomes clear that the work will not finish on time for a reason not attributable to the client (see the article text for the conditions). If it is clear during production that the work will be defective through the contractor’s fault, the client may set a suitable period for the defect to be remedied and state that, failing this, repair or continuation will go to a third party Track the lead time in writing and use a written, dated notice rather than a verbal warning. Withdrawal is a heavy step; consult a lawyer first
Inspection on delivery (Arts. 474, 477) The client must inspect the work as soon as practicable after delivery and notify defects within a suitable period; if it neglects to, it is deemed to have accepted the work. After acceptance the contractor is released from liability, except for defects deliberately concealed and not noticeable on inspection; a later defect is also deemed accepted if not notified without delay (Art. 477/3) Write the delivery and inspection timetable into the agreement; do not sign an acceptance document before inspecting; notify findings in writing, with photographs
Defective work (Art. 475) The client chooses one right: withdrawal, if the work is so defective that it cannot be used or cannot fairly be forced on the client; keeping the work and reducing the price in proportion to the defect; or free repair, if it does not require excessive cost. Damages under the general provisions are reserved Write the rework, sorting and price-reduction procedure and its time limits in advance

The law says “a suitable period” for notifying defects and gives no number of days, so what that means in a specific case can be disputed. Set the inspection and notification periods explicitly in the agreement. This table is not legal advice; have a lawyer prepare or review your agreement. The clauses an agreement should contain are covered in the article on the contract manufacturing agreement.

VAT and invoicing

As of the date of this article (October 8, 2026), section I/C-2.1.3.2.7 of the Turkish VAT General Implementation Communiqué places contract textile and clothing work under partial withholding; the withholding is applied by the buyer groups listed in the Communiqué. Auxiliary materials used by the workshop, such as thread, zips, buttons, interlining and lining, are included in the contract-work fee and are not invoiced separately. For the rate and a worked example, see the article on VAT withholding on contract sewing. Legislation can change; always clarify the invoicing method with your accountant. This section is not tax advice.

Control points during production and on delivery

Material intake and fabric accounting

With CMT, if you send the fabric, the process begins with the fabric shipment. Our recommendation as Tekstil Rehberi: write the number of rolls and the metres or kilograms on the dispatch note; ask the workshop to count and check the fabric on receipt (width, weight, shade variation and fabric defects) and to report findings immediately. The law also puts a duty of immediate notification on the contractor if the material turns out to be defective (Art. 472/3). After cutting, produce a fabric account: fabric received, fabric cut, wastage and leftover fabric should reconcile, and the return of leftover fabric also depends on this account (Art. 472/2).

Pre-production approval and in-line checks

Bulk production should not start without an approved sample and a pre-production (PP) approval; for the sample stages see the article on the sampling process. Once production starts, in-line checks do two things: defects are caught before they spread across thousands of cut pieces, and a dated record is created. If you notice that defective production is continuing, reporting it in writing also keeps open the notice route described in the table above.

Acceptance and handling defects on delivery

Carry out a sampling-based final inspection on delivery: measurements, sewing, appearance, labels and packing. The usual sampling method in garments is AQL (acceptable quality limit); see quality control and AQL sampling for how it works. Tie the findings to a written acceptance or rejection, and do not sign for acceptance before inspecting (see Arts. 474 and 477). If a defect is found, the procedure you wrote into the agreement applies: rework, sorting, price reduction. If you want to buy in quality control as a service, see the quality control firms page.

Common mistakes in contract manufacturing

  1. Leaving the scope verbal. The word “fason” does not say who supplies what; the TDK definition and the VAT Communiqué also turn on who holds the materials. Write every item into the quote and the agreement.
  2. Not recording sample approval, and changing the style after approval. Changes made after approval without adjusting price and time put pressure on the manufacturer (SOMO, 2015).
  3. Delivering fabric without a count and not asking for a fabric account. Disputes over wastage and leftover fabric can only be settled with records.
  4. Not asking about capacity. A lead time given without knowing the jobs the workshop has taken at the same time, or its headcount, can remain a wish.
  5. Not giving subcontracting permission, or never discussing it. Without a written rule you may not know where the work is done; according to SOMO (2015), your social compliance audits also do not reach those workshops, and your quality follow-up becomes just as hard.
  6. Accepting delivery without inspecting. After acceptance the contractor is released from liability, except for defects that were deliberately concealed and could not be noticed (Art. 477).

Questions to settle before you accept a quote

For a buyer placing an order with a Turkish workshop, the sections above reduce to seven questions:

  1. Which model is this quote — CMT, full package or sewing only — and who supplies each item?
  2. If the price says “FOB”, does it mean full-package production, and which delivery point and port does it assume?
  3. Do you subcontract any stage? If so, which one, to whom, and only with my written permission?
  4. What SMV and efficiency does the lead time assume, and how many direct operators will run my order?
  5. Does the lead time include fabric intake, cutting, pressing-and-packing and shipping, or only sewing?
  6. Who approves the sample and any later changes, and through which channel?
  7. How will the order be invoiced, and which inspection and notification periods apply on delivery?

Next steps

Once you have chosen your model, the next step is selecting a workshop and comparing quotes: screen candidate workshops with the criteria in the article on choosing a contract workshop, and put the quotes side by side using the method in the article on contract T-shirt sewing prices (both are linked in the sections above). You can browse firms that do contract sewing on the CMT sewing workshops page. The production models and cost framework here are general information; take advice on your agreement, invoicing and tax decisions.

Frequently asked questions

What is the difference between CMT and full package (FOB) production?

According to the definitions in a World Bank study, in CMT (cut, make, trim) the factory is paid for the process, not the product, and the buyer supplies the fabric. In full-package production the factory sources and finances the fabric and trims, completes production and packs the goods. FOB is in fact a delivery term, but the trade also uses it to mean full-package contract production. Because the Turkish dictionary (TDK) and the Turkish VAT General Implementation Communiqué define contract work by the materials being supplied by the party commissioning it, ask the supplier and its accountant how work is invoiced when the workshop supplies the materials.

What does “fason” mean on a Turkish quotation, and does it mean counterfeit?

“Fason” is the Turkish trade word for contract manufacturing: the Turkish Language Association dictionary (TDK) defines “fason üretim” as production placed with another firm, with the materials supplied by the brand owner. It is an ordinary commercial relationship recognised in legislation; for example, the Turkish VAT General Implementation Communiqué sets separate rules for contract textile and clothing work. The TDK dictionary also records a dialect sense of “fason” as “an imitation product made illegally”, but that is a different usage from commercial contract manufacturing. Making an unauthorised copy of a brand is not contract manufacturing: under Industrial Property Law No. 6769 it counts as trademark infringement and carries criminal penalties (Arts. 29–30). For tax, social-security and licensing obligations, consult an accountant and a legal adviser.

What steps do you follow to have a garment made by a contract manufacturer?

The order is: define the product and scope; prepare the tech pack and brief; collect at least three quotes for the same scope and choose a workshop; settle the agreement and the invoicing method; approve the sample and the pre-production sample; ship materials and check the fabric on arrival; monitor production; inspect on delivery and close out. Keeping the output of each step in writing reduces disputes later.

Can a contract workshop pass your order to another workshop?

Under Art. 471 of the Turkish Code of Obligations, which governs contracts for work, a contractor may have the work done by someone else if its personal qualities do not matter. Whether this provision applies to your relationship depends on the content of your agreement, so write a written-permission and notification requirement for subcontracting into the contract. Short lead times, late-arriving fabric and exceeded capacity are among the reasons for subcontracting that SOMO (2015) lists.

What can you do if the factory delivers late or delivers defective goods?

Start with the procedure in your agreement. If the agreement is silent, the contract-for-work rules of the Turkish Code of Obligations may come into play: the client’s right to withdraw if it becomes clear that the work will not finish on time (Art. 473); a notice with a deadline if defects become visible during production (Art. 473); inspecting the goods after delivery and notifying defects within a suitable period (Arts. 474 and 477); and, for defective work, the rights to withdraw, reduce the price or have free repair (Art. 475). Your lawyer decides whether these provisions apply to your order; take advice before steps such as withdrawing from the contract.

How can you tell whether a workshop can meet the delivery date?

A simple capacity check helps: multiply the direct operators on the line by the net working minutes per day and by efficiency, then divide by the standard minute value (SMV) of the style; the result is daily output. Divide the order quantity by daily output to get the working days the sewing line needs. Fabric intake, cutting, pressing-and-packing and shipping sit outside this calculation. Ask the workshop for its SMV and efficiency assumptions in writing.

Related calculator

Sources (11)

  1. TDK Güncel Türkçe Sözlük (Turkish Language Association dictionary), entries “fason üretim” and “fason” (accessed October 8, 2026)
  2. Gereffi, G. and Frederick, S. (2010). The Global Apparel Value Chain, Trade and the Crisis: Challenges and Opportunities for Developing Countries. World Bank Policy Research Working Paper 5281
  3. U.S. International Trade Administration, Know Your Incoterms (Incoterms 2020, FOB) (accessed October 8, 2026)
  4. Turkish Code of Obligations, Law No. 6098, Articles 470–478 (contract for work; Turkish text)
  5. Court of Cassation (Yargıtay) 15th Civil Chamber, 2017/2037 E., 2018/3366 K. (24.09.2018) and 2018/3517 E., 2019/1255 K. (20.03.2019) (contract-for-work relationship in contract sewing; Yargıtay case-law search, Turkish)
  6. Industrial Property Law No. 6769, Articles 29–30 (trademark infringement; Turkish text)
  7. Turkish VAT General Implementation Communiqué (Official Gazette, April 26, 2014, No. 28983), Revenue Administration (GİB) legislation page, section I/C-2.1.3.2.7 (contract textile and clothing work; Turkish text)
  8. SOMO, Hidden subcontracting in the garment industry: Zooming in on the role of buying companies (Fact Sheet, September 2015)
  9. Republic of Türkiye Ministry of Trade, General Directorate of Exports, Ready-to-Wear Sector Report 2026 (Turkish)
  10. ILO, Introduction to Work Study, 4th (revised) edition, 1992 (standard time expressed in standard minutes, p. 336; performance rating, p. 434)
  11. PLMA, Store Brand Facts: What Are Store Brands? (accessed October 8, 2026)

Author and fact-checking

Written by

Zeynep Arslan

Contract Manufacturing and Workshop Editor

Zeynep Arslan is Tekstil Rehberi's contract manufacturing and workshop editor. She writes practical guides on CMT pricing, contracts, tax obligations such as VAT withholding, setting up a workshop and incentives, and takes tax and regulatory details from official sources in force on the date of writing.

Content by Zeynep Arslan

Fact-checked by: Gizem Polat

This content was prepared by the Tekstil Rehberi editorial team. Before publication, our verification editor checked its figures, dates and sources against primary sources.

Spotted an error? Email us at [email protected] How we work →